Abstract

The price of concrete items IS affected by the productivity of manpower and concrete equipment.
‎The price is divided into the direct cost and the mark-up. The direct cost includes the materials, manpower, formwork, equipment and subcontractors cost.
‎The mark-up is subdivided into the following parts: site overhead, office overhead, Taxes, insurance, stamps, and profit.
‎The cost control fur project should be applied during the execution of the project in order to avoid any unexpected delaying or any negative variance in the cost or in the time.